Mackintosh-Corry Hall lighting retrofit - April 17-22

Crews are continuing to work on the project to retrofit the existing lighting systems in Mackintosh-Corry Hall that are still utilizing T12 technology. Attached is a fixture schedule by room for the period of April 17-22, 2017.

Scope of the Work

Lighting systems have been audited on a room by room basis. Individual actions for each room have been broken down into three possible actions:

1. Retrofit (Replace components (lamps, ballast and end clips of existing fixtures)
2. Remove and replace (Replace fixtures with new light fixture)
3. Redesign (Removal all fixtures and conduit, install new layout of fixtures and conduit, paint entire ceiling)    

PAINTING UPDATE>>>  The painting crew worked in rooms A517 to A524  on April 17. The crew will be working in rooms A516, 511, 512, 509, 510, 508, 507, 506 on April 18 and in rooms A505, 504, 503, 502, 501 on April 19. The painting schedule through April 27 is also attached for your reference.

Hours of Work: From 5 pm to 3 am or 5 am

Any questions about this project should be directed to Fixit at ext. 77301 or by email.