Residences construction update: July 8

  • Lower Albert St. will be closed for the week to complete the water and gas service installation.
  • Deliveries of equipment and materials will continue daily with a lane closure on Stuart St. on July 16 to hoist major equipment to the roof. Stuart St. will be completely closed the following day (July 17) to dismantle the tower crane.
  • Work on the Albert St. building continues with intermittent concrete deliveries for steam trenches and miscellaneous concrete. Contractors are respecting 7:30 am to 7 pm work hours. 