Program Timeline

The program timeline below illustrates the current working schedule that has been developed.  As the information gathering process continues the schedule may be fine tuned.  In advance of the onsite audits, notice will be posted regarding which buildings Honeywell intends to tour each week.  

Schedule

Start

Finish

Weeks

Kick-off Meeting

10-Jan-14

10-Jan-14

0.0

Data Collection

13-Jan-14

31-Jan-14

3.0

Utility Analysis

03-Feb-14

21-Feb-14

3.0

CHP Audit

06-Feb-14

07-Feb-14

0.1

BAS Audit

04-Feb-14

07-Feb-14

1.0

Building Audits (2 teams)

24-Feb-14

28-Feb-14

1.0

Building Audits (2 teams)

03-Mar-14

07-Mar-14

1.0

March Break (no audits)

10-Mar-14

14-Mar-14

 

Building Audits (2 teams)

17-Mar-14

21-Mar-14

1.0

Building Analysis

24-Mar-14

09-Apr-14

2.5

Report Generation

10-Apr-14

23-Apr-14

2.0

Project Review

24-Apr-14

29-Apr-14

0.7

Report Presentation

30-Apr-14

30-Apr-14

0.0

 

 