As the holidays approach, work on site will focus on concrete pouring and earthworks. On Saturday, December 19, some limited demolition at the back of 142 Albert will be completed. The original portion of the house is being retained and incorporated into the new residence building.
Work on site will continue up to and including December 24. Work will shut down December 25-28, with workers back December 29-31, before closing down again for New Years from January 1-3, 2021 (inclusive). Regular work, including rock removal, will resume January 4, 2021.
We wish you all a safe and joyous holiday season and a Happy New Year. Our next update will be January 8, 2021.
Should you have any questions or concerns, please contact us at newresidenceproject@queensu.ca.
Construction Impact Forecast · Dates are accurate at time of reporting, but could be subject to change due to weather and other factors · Work will take place between 7 AM – 7 PM |
||
Date(s) |
Activity |
Neighbours may notice |
December 19 |
Limited demolition at rear of 142 Albert Street |
General construction noise |
December 25 - 28 |
HOLIDAY SHUTDOWN |
quiet |
December 29 - 31 |
Site work resumes |
General construction noise |
January 1 – 3, 2021 |
NEW YEARS’ SHUTDOWN |
quiet |
January 4, 2021 |
Regular work resumes |
Concrete pouring, rock removal |