A summary of residences construction activity from September 15 - 19.
- Concrete sidewalks in front of McNeill House and behind Morris Hall and Gordon and Brockington Houses may cause detours but exits will remain available for emergencies.
- Infrastructure for the new communication routing is complete but will be extended into Morris Hall which may affect pedestrian circulation around the Albert Street entrance.
- Congestion due to construction vehicles and equipment/material deliveries continues.
- Security guards will be stationed after-hours around construction sites.