- Storm sewer and water main excavation continues to progress north on George Street, currently in the intersection of George Street and O’Kill Street.
- Crews will soon begin the replacement of sidewalks in the lower portion of George Street (between King Street West and O’Kill Street), along with road building and street light installations.
- Work has been completed on the sanitary main in the park at the foot of George Street. Crews will continue working in the area to restore the surface of the park in time for Remembrance Day ceremonies.
- Temporary asphalt is now in place in the intersection of George Street and Stuart Street. Excavation work will return to the intersection in the coming weeks, however temporary asphalt will allow for reduced dust and smoother vehicle ride through the intersection. Permanent asphalt will be laid in the intersection, along with the rest of George Street, once excavation work is completed.
Roadwork construction update