- Crews expect sidewalk pouring on George Street to be completed by the end of this week.
- With all excavation works complete, crews will begin the grading of George Street early next week. Once grading is completed, crews will be on site to pave the base layers of asphalt on George Street, which will be completed by the end of next week, weather dependent.
- Outside of sidewalk and road building activities, crews will be cleaning up the construction site in preparation for the winter shutdown. Crews will need to return in the spring of 2015 to complete the paving of the final layer of asphalt on George Street.
- As a reminder, crews will be returning in 2015 to complete similar reconstruction work on Arch Street, O’Kill Street and Stuart Street between Arch Street and Lower University Avenue.
Roadwork construction update