A summary of roadwork activities for the week of August 3.
- Crews have returned to Arch Street to complete the sewer connections and the installation of manholes. As a result, the intersection of Arch and Stuart Streets is closed and vehicles must exit Arch Street via Union Street. The intersection of Arch and Stuart Streets is expected to re-open early next week.
- Pipe work has been completed in the intersection of George and Stuart Streets. Some minor finishing works are taking place and work will begin next week to fill the trench in the intersection. Once work is completed on Arch Street crews will return to Stuart Street to complete work on Stuart Street between George Street and Lower University.
- Barring any unforeseen circumstances, it is anticipated that excavation work on Stuart Street will be completed in the next two to three weeks. There will still be electrical and restoration work to take place after the completion of excavation work.