As part of the ongoing energy conservation project under the banner of CAPit, crews from Honeywell will be completing work relating to building envelope measures (installation of sealing such as caulking and/or weather stripping) in the following buildings June 20-29:
- Jackson Hall – June 20-21 (windows and doors, offices)
- Old Medical Building – June 21-23 (windows and doors)
- Bruce Wing - June 21-24 (doors only)
- Sir John A. Macdonald Hall – June 21-29 (windows and doors, a few offices, mostly classes, corridors and conference spaces)
- Mackintosh-Corry Hall – June 21-24 (windows and doors)
- Nicol Hall – June 27-29 (windows and doors)
The work crew typically goes through a building assessing spaces/offices that are not occupied and uses that opportunity to communicate with those in occupied offices regarding the scope and scheduling of this work. Occupants should remove all personal belongings from window ledges in advance of crews arriving to their buildings.
If there are any concerns about the schedules proposed above or if security personnel need to be present while crews access any of the affected areas, please contact Joe Furo, Honeywell Site Coordinator, by phone at 613-978-6070.
More information about CAPit can be found on the Queen’s Sustainability Office website.